Municipalities with more than 20,000 and less than 50,000 inhabitants have until December 5, 2026 to adopt a sustainable mobility plan. This is required by Article 24 of Law 9/2025 on Sustainable Mobility, which gave them one year from its entry into force.
The deadline that expires on that date concerns municipalities. Companies have until December 5, 2027 for facilities with more than 200 workers, or 100 per shift. This is stated in Article 26 of the same law.
One year from December 2025
The law was published in the Official State Gazette on December 4, 2025. Its twenty-second final provision fixes the entry into force for the following day, December 5.
Article 24.1 gives these municipalities “one year from the entry into force” to equip themselves with the plan. Read this way, the deadline ends on December 5, 2026.
The law calls it the “simplified local government mobility plan.” It must be reviewed at least every six years, unless the regional law sets a different pace.

What the municipal plan must include
The plan must include measures to regulate the urban distribution of goods. To do this, the municipality must cooperate with neighboring municipalities and seek common criteria.
Every three years, the municipality will prepare a report on how much of the plan has been fulfilled. The plan, its revisions, and these reports are communicated within three months to the authority designated by the autonomous community.
Those documents will be public, according to Article 27. They will be entered into a plan registry, within the Integrated Mobility Data Space.
The plan, tied to subsidies
The law links the plan to funding for urban transport. Article 58 specifies who can apply for subsidies for urban public transport. They come from the State Fund for Contribution to Sustainable Mobility, which is created by Article 56.
Applications can be submitted, among others, by municipalities with more than 20,000 inhabitants and provincial capitals. But subsection 4 imposes a condition: to be beneficiaries, they must have a sustainable mobility plan in accordance with Article 24.
The largest municipalities, since 2023
Municipalities with more than 50,000 inhabitants do not initiate this obligation. Law 7/2021 on Climate Change already required them, in its Article 14, to have plans for sustainable urban mobility before 2023. This is the case of Vitoria, whose mobility plan for 2026–2030 proposes to reduce 7,500 car trips per day.
Those plans had to include, at a minimum, low-emission zones before 2023. They also included measures to walk, cycle, or use public transport. Three years later, some town halls still do not have them.
Autonomous communities can go further. According to Article 24.2, they can recommend or require the plan from other municipalities, from groups of municipalities, or from supra-municipal entities.
If a municipality is part of a supra-municipal entity obliged to have a plan, that obligation replaces the municipality’s own obligation.
Companies, one more year
Article 26 gives companies 24 months from the entry into force. That extends their deadline to December 5, 2027.
The obligation affects sites with more than 200 people who work there regularly, or 100 per shift. It also applies to public sector entities with centers of that size.
The plan is negotiated with the workers’ legal representation. If there is none, a negotiating committee is created between the company and the most representative unions and those in the sector.
What measures do they require of companies
The law provides examples of what they may include. It speaks of walking or cycling, of public transport, and car sharing. It also references charging of electric vehicles and teleworking, when possible.
It also calls for road safety measures in the journeys to work. And that the plan takes into account visitors and suppliers, not only the workforce.
In centers with more than 1,000 workers, located in municipalities or metropolitan areas with more than 500,000 inhabitants, there are more requirements. They must include measures to reduce commuting during peak hours or during the working day.
Two years after approving the plan, the company will prepare a follow-up report, and then another every two years. As assistance, the Ministry of Transport will authorize grant calls for companies with centers of more than 100 workers, or 50 per shift.
To comply, the company can also provide its staff with transport cards managed by a card-issuing company. This is done under the terms already provided by the Personal Income Tax Law (IRPF).